Start office move IT planning eight weeks ahead. Order internet first because it has the longest lead time, schedule phone number porting, get cabling in before move week, take a tested backup, and move over a weekend with a technician on site the first morning.
- Internet installs are the most common reason moves go wrong.
- Port phone numbers on a scheduled date.
- Label every device with its new location.
- Movers move boxes. Someone needs to own the IT.
The move timeline
| When | What to do |
|---|---|
| 8 weeks before | Walk the new space, order internet, plan the network |
| 6 weeks before | Schedule phone porting, plan cabling and power |
| 4 weeks before | Cabling installed and tested, network closet ready |
| 2 weeks before | Firewall, switches, Wi-Fi and phones installed |
| 1 week before | Inventory and label devices, full tested backup |
| Move weekend | Disconnect, pack, move, reconnect and test |
| Monday | Technician on site for the first morning |
Internet first
Business internet installs, especially fibre to a new building, can take weeks. Order as soon as the lease is signed and confirm the install date in writing. Where uptime matters, order a backup connection from a different provider.
Phone numbers
Moving to a new address may mean moving phone service. Schedule porting for the move weekend and keep the old service live until the port completes. Update 911 civic addresses for VoIP lines.
Cabling and the network closet
Plan drops for every desk, printer, camera, access point and meeting room screen. Get cabling in before furniture arrives. Make sure the closet has power, ventilation and space for a rack and UPS.
Move weekend checklist
- Friday evening. Final backup, shut down systems in order, disconnect and label.
- Pack sensitive gear yourself. Servers, firewalls and switches should not travel loose in a truck.
- Saturday. Install network gear, power up servers, connect desks.
- Sunday. Test every desk, printer, phone and the internet.
- Monday. A technician on site to handle anything missed.
Leaving the old site
- Remove all equipment and cabling you own.
- Wipe or destroy drives in anything left behind.
- Return keys, fobs and access cards.
- Cancel old internet and phone services after the move.
Quick answers
How far ahead should we plan IT for an office move?
Eight weeks is ideal. Internet lead times are usually the limit.
Should we move over a weekend?
Yes, if you can. It gives a full day to test before staff arrive.
Can we reuse our old network equipment?
Often. It is also a good time to replace old switches and Wi-Fi.
Who should be responsible for IT during the move?
One person or provider who owns the whole IT plan.